EIA Study and Design of Gortu Bridge and Approach Roads
Review of hydrological calculations and flood estimate, Environmental Impact Assessment Study, structural design, preparation of drawings and detailing, cost estimates and tender documents of a 120 m long bridge comprising 3 spans each measuring 40 m, bridge protection works, river training works, and review of geometric designs of 500 m approach roads on either side of the bridge. The project bridge is across River Ewaso Nyiro
The Total Construction Cost was Kshs 500 Million